CONSTRUCTION COMMENCEMENT NOTICE
Notices are being delivered today for residents along Plante Dr. in relation to the City’s sewer rehabilitation work in the neighbourhood. This is in relation to work to be performed on the National Capital Commission lands on the easement north of Plante Drive.
The clearing and video work is tentatively planned to start during the evening of Monday, January 16th and is anticipated to be completed by Friday, January 30th, 2015. This work is being done primarily at night. The second stage of the project will begin approximately Monday, February 23rd and should take approximately five days to complete.
To view the letter from city officials that is being delivered to affected homeowners, please click on the image below.
Any question related to this project can be directed to the City’s Project Manager: